Location
Carlisle, PA
Project Details
CASD consisted of installation of 5,000 feet of 2” diameter HDPE conduit through downtown and surrounding areas of Carlisle via horizontal directional drilling. 950 LF of 2” HDPE was drilled under the PA Turnpike. 300 feet of 4” steel casing was drilled under an existing Norfolk Southern Railway. A 72-strand fiber optic cable was installed through the HDPE conduits.
Final Product
29,700 feet of fiber optic cable via directional drilling and open cut.
Geology
Limestone
Completion Date
July 2016
Installation Methods
- Horizontal Directional Drilling