Location
Washington, DC
Project Details
A short crossing under 4th St. in Washington DC was needed to tie an inlet into the larger Anacostia River Project while keeping the roadway open to one way traffic. Soil borings suggested the presence of flowing ground. The work crew pumped permeation grout above the crown of the proposed crossing to solidify the soil prior to jacking a 60” diameter steel casing under the roadway.
Final Product
15 LF of 60” Steel Casing
Geology
Loose and running gravel, sand and silt
Completion Date
December 2020
Installation Methods
- Pipe Jacking and Tunneling
- Soil Stabilization
- Grouting